Project Description & Outcomes
This project involves multiple best management practices in order to reduce phosphorus loading to Moody Lake by a total of 62 pounds per year and reduce sediment loading by a total of 8,940 pounds per year. CLFLWD performed diagnostic monitoring and site-specific wetland coring to target remaining nutrient loading hotspots in the direct drainage area. Proposed projects include: agricultural field gully repair, excavation of phosphorus-laden soils, raingarden and other park improvements, and wetland dredging.
Watershed load reduction goals were identified as a result of the Moody Lake Diagnostic Study.
The CLFLWD received a $239,500 Clean Water Fund (CWF) grant from the Board of Water and Soil Resources (BWSR) for this project.
Project Status
In-Progress
Project Outcomes
62 lbs/yr phosphorus removal
8,940 lbs/yr sediment removal
0.8 acre-ft flood storage added
0.50 acres wetland restored
Financials
Clean Water Fund Grant: $239,500 (Grant Report)
CLFLWD Grant Match: $59,875
Total Project Budget : $299,375
Lifecycle cost varies by practice:
Average $400 per pound of phosphorus removed
(What does this mean?)
Timeline
2022: Project development and design
2023-2024: Project Construction